COVID-19: impacts on government contracts and contracting
Shrinking global commerce and the closing of land and air borders to avoid the spread of COVID-19 have had impacts not only on the public health sector, but on government contracts and contracting, administrative proceedings, and the supervision and control of government acts, profoundly affecting relations between the private and public sectors. Click on the titles to read the whole article.
Federal Law 8666/1993 (the Government
Contracting Law) allows government contracting processes currently underway to
be cancelled or postponed for reasons of public interest in view of the
COVID-19 pandemic, without liability to the companies participating in the bid.
If because of COVID-19 a contracting process is not concluded before submitted bids expire, and the government later requests an extension, participating companies are not required to maintain the terms of their bids, but they can do so if it is in their interest.
When it is no longer viable to maintain a contract for supply of goods or services, whether because of the COVID-19 public health emergency, or for another reason set out in article 78 (XII) to (XVII) of the Government Contracting Law (Law 8666/1993), the government entity can terminate the contract.
Federal Law 13.979/2020, which establishes
measures related to COVID-19, provides that competitive bidding procedures can
be waived for the acquisition of health-related goods, services and inputs that
will be used to deal with the public health emergency.
Among the measures implemented by the government
to deal with the COVID-19 crisis are more flexible contracting procedures to
speed up the procurement process. These more flexible rules do, however, mean
that suppliers should take added precautions, and reinforce their internal
controls to avoid future problems raised by authorities responsible for the
supervision and control of public accounts and government contracts.
Unforeseen events related to COVID-19 that upset
the economic and financial balance between the parties, and consequently
performance of government contracts, are triggers for requests to re-establish
the balance under the contract, as provided for in article 65(II)(d) of Law
8666/1993.
The measures adopted by government in connection
with the COVID-19 emergency can made it difficult or even impossible to perform
contracts with the government.
Among the other measures introduced by Federal Law 13.979/2020 to deal with the COVID-19 crisis is the requisition of goods and services from individuals and legal entities, against payment of fair compensation in the future (article 3(VII)).
On 23 March 2020, the Federal Government
published Provisional Measure 928, suspending the deadlines for responses to
requests for information made under the Access to Information Law to public
authorities that are in quarantine or working from home and that depend on (i)
physical access to records by public agents, or (ii) public agents who are
involved on a priority basis to combating COVID-19.
In addition to temporarily changing the rules on
requests for information under the Access to Information Law, Provisional Measure
928 of 23 March 2020 (“MP 928” – Medida
Provisória 928) suspends filing deadlines that run against respondents and
private entities in administrative proceedings, while the state of emergency
brought on by COVID-19 exists
In the current crisis, public authorities in the
judicial, executive and legislative branches of government will be focused on
fighting COVID-19 and its impacts, through various measures such as decisions
and new legislation and regulations. Here in BMA’s Compliance, Investigations
and Enforcement practice area, we believe that the same spirit should drive
compliance personnel in the private sector. Our team has put together some tips
on how companies can strengthen compliance in connection with the use of
technology in home-based work, which has become widespread in the COVID-19
pandemic.